PCCE #8 Thilly-Lathrop-Westmount

Construction Year: 2017/2019
Project Budget:
$2,200,000
Funding Source:
2013 Sewer Bond
Year Completed:
 


Project Description: 
Thilly-Lathrop-Westmount Sanitary Sewer project will consist of constructing sanitary sewer mains (approximately 6,934 linear feet), and will include new private service connections and replacement of service laterals, as required to reconnect the existing structures to the new sewer main as shown on the attached diagram. There are seventy one parcels affected by this project

Project Status:  Phase 1 & 2 complete, Phase 3 Under Construction

Project Manager: Nathan Runyan, P.E.

Construction by: Tim Harris Excavation

Interested Parties Meetings: Oct. 24, 2012; Mar. 9, 2015; Oct. 27, 2016