PCCE#16 Bingham – Ridgeley

Construction Year: 2018/2019
Project Budget:
$1,800,000
Funding Source:
2013 Sewer Bond
Year Completed:
 


Project Description: 
Bingham – Ridgeley Sanitary Sewer project involves construction of new public sanitary sewer mains to serve forty-five (45) parcels of land along Bingham Road and Ridgeley Road, with forty (40) of these parcels currently being served by private common collector sewers (PCC). This project will consist of constructing approximately 3,290 linear feet of gravity sewer mains and will include new private service connections and extension of service laterals as necessary to reconnect the existing structures to the new sewer main.

Project Status:  Phase 1 construction began October 2018

Project Manager: Lee White, P.E.

Construction by: Twehouse Excavating

Interested Parties Meetings: Oct. 24, 2012; Mar. 9, 2015; Oct. 27, 2016

Public Hearing:  May 15, 2017; opens in a new windowView Memo

Location/Design: 

opens in a new windowPCCE #16 – Map Diagram