Vandiver and Parker Roundabout

Funding Fiscal Year: 
 Design 2017/Construction 2018
Ward
2
Project Number:
 C00645
Project Budget:
$900,000
Funding Source:
2015 Capital Improvement Sales Tax
Year Completed:
 

 

Project Description: The current two-way stop  at this intersection will be removed and replaced with a single-lane roundabout. The roundabout will include splitter islands and sidewalks. It will be able to accommodate larger commercial vehicles and school buses. An additional 300 feet of the west leg of the roundabout on Vandiver Drive will be reconstructed to improve sight distance. Street lighting will also be installed.

https://www.como.gov/citychannel/2019/10/10/vandiver-parker-roundabout/

Project Status:   Completed.

Contractor:  S&A Equipment and Builders

Public Works Project Manager: Nazmul Hussain, P.E.

Interested Parties Meeting: May 10, 2017

Public Hearing: July 3, 2017

Press Releases:

Project Information:

Roundabouts: CoMo.gov/PublicWorks/traffic/intersections


Progress Updates: 

 

Oct. 14, 2019: Seeding and the center island  landscaping were completed in early 2019. See video.

Dec. 20, 2018: 

The roundabout opened on Dec. 19. The contractor is continuing to work on the sidewalks and other aspects of the project.

 

Dec. 18, 2018: 

Line striping, sidewalk construction and other work continues.

line stripingsidewalk construction

Nov. 30, 2018: 

S&A Equipment and Builders, the contractor for the Vandiver-Parker Roundabout project, says it’s taking advantage of warmer weather Thursday – Saturday to work on the last leg of the project. Completion of the project is tracking early/mid December. Vandiver Drive remains open with alternating traffic and detours. 

roundabout construction

pouring roundabout concrete

Oct. 17, 2018: 

Crews are finishing the westbound pavement on the west leg of the roundabout between Parker and Veteran’s United this week. The lane is being lowered and reconstructed to improve the sight lines for traffic approaching the roundabout. At some point early next week, the westbound lane will open to traffic and the eastbound lane will close for reconstruction. Traffic will continue to be regulated by a traffic signal on each end of the project, allowing traffic to use the lane in alternating directions. The project continues to be on schedule for completion by early December, weather permitting.

 Central Concrete delivers a load of cement for the Vandiver-Parker roundabout project.
 The west leg of the roundabout on Vandiver is being lowered and reconstructed to improve sight distance. The section is between Parker and Veteran's United on the west side of the roundabout.