Third Avenue Alley Restoration

 

Funding Fiscal Year: 
2019
Ward
1
Project Number:
C00734
Project Budget:
$150,000
Funding Source:
Transportation Sales Tax, 2015 Capital Improvement Sales Tax
Year Completed:
 

Project Description: The improvement project will include constructing a 10-foot wide asphalt pavement (see location and layout diagrams below) within the alley right-of-way of Third Avenue (between Garth Avenue and Grand Avenue.)

Project Status: A Public Hearing for final approval is scheduled on April 1, 2019.

Project Manager: Allison Anderson, P.E.

Interested Parties Meeting: Feb. 21

Public Hearing date: April 1, 2019

Press Releases: Feb. 12, 2019

Project Information: