Oakland Gravel Road Sidewalk (Blue Ridge to Edris)

Funding Fiscal Year: 
 Design 2017/Construction 2018
Project Number:
 C00660
Project Budget:
$311,500
Funding Source:
2015 Capital Improvement Sales Tax
Year Completed:
 

 

Project Description: This project will fill in the sidewalk gap along the west side of Oakland Gravel Road between Blue Ridge Rd and Edris Road

Project Status: The City is working on final plans and easement acquisition for this project.

Project Manager: Allison Anderson, P.E.

Interested Parties Meeting:  June 14, 2017.

Public Hearing: Sept. 5, 2017

Location Map: Oakland Gravel Road sidewalk (Blue Ridge to Edris)

Project Layout: Proposed Oakland Gravel Road Sidewalk Plans (Blue Ridge to Edris):  1  ; 2 ; 3

Public Hearing Council Memo: Aug. 7, 2017