Nifong Intersections Improvement (Sinclair, Old Mill Creek)

 

 

Funding Fiscal Year: 
Design 2016/Construction 2020
ward
5
Project Number:
C00644
Project Budget:
$2,450,000
Funding Source:
2015 Capital Improvement Sales Tax ballot
Year Completed:
 

Project Description: Two roundabouts will be constructed on Nifong Boulevard, at Sinclair Street and Old Mill Creek Road, to improve safety, reduce queue lengths and decrease travel times by the removal of four-way stops and the installation of more efficient and sustainable intersections.  These roundabout will be single-lane roundabouts, expandable to partial dual-lane roundabouts. Vawter School Road and Country Wood Road also intersect at the Old Mill Creek Roundabout. 

Roundabout Benefits

Project Status: Construction planned to begin April 27, 2020, and be completed by fall 2020.

Contractor: Emery Sapp & Sons Inc.

Project Manager: Allison Anderson, P.E.

Designer:  Bartlett and West

Interested Parties Meeting: June 20, 2017

Public Hearing: Oct. 16, 2017

Press Releases:

Project Information:


Construction Updates:

April 13, 2020: Social media location diagrams:

Nifong and Sinclair:

Nifong at Sinclair roundabout begins April 27 with closure on south leg at Sinclair 

Nifong and Old Mill Creek:

Nifong at Old Mill Creek construction begins May 4