Nifong Boulevard Corridor Improvement Project

Funding Fiscal Year: 
Design 2017/Construction 2020
Project Number:
C00631
Project Budget:
$12,300,000
Funding Source:
2015 Capital Improvement Sales Tax
Year Completed:
 

Project Description: This improvement would add two additional through lanes, bike lanes, sidewalks and intersection improvements along Nifong between Providence and Willowcreek, and along Forum between Nifong and Green Meadows. (Two new streets–Aurora Drive and Nova Way–will be constructed by a private developer.) The project also includes a traffic signal at the new intersection of Nifong and Aurora Drive. 

Project Status: The consultant is working on the final plans for the corridor’s improvements.

Contractor(s): Engineering Surveys & Services

Project Manager: Allison Anderson, P.E.

Interested Parties (IP) Meetings: 

Public Hearing: 

7 p.m., Jan. 16, 2018, City Hall 

Project Plans

Press Releases:

 


Return to Current CIP Projects