Mill and Overlay 2019

Mill and Overlay 2019

Mill and overlay involves milling off the top of the pavement surface and then applying a layer of asphalt back to create a smooth driving surface. Sometimes a street is not milled but simply overlaid with asphalt. The goal is to extend the life of the roadway for an additional six to 20 years. See the City of Columbia’s Pavement Management Plan for more information.

Progress Updates:

Dec. 17, 2019: The work on sections of four streets was postponed by the contractor until Spring/Summer 2020.


Capital Paving:

Road From To Agency Schedule
Ballenger Lane Mexico Gravel Road Just north of Ria Street Capital Paving Completed
Mexico Gravel Road/Ballenger Lane Roundabout  Capital Paving Completed
Brown School Road  Range Line Street

500 feet west of the Brown School Road and Range Line Street intersection

Postponed
Sandman Lane  Nifong Boulevard South End Postponed
Cooper Drive Buttonwood Drive

West End

Postponed

South Ponderosa Street/Nocona Parkway 

Roundabout

Postponed
Towne Drive Clark Lane Sylvan Drive Capital Paving Completed
Whitegate Drive Paris Road Lambeth Drive Capital Paving Completed
Blue Ridge Road/Brown Station Road Intersection Capital Paving Completed
Clark Lane Paris Road Bridge Capital Paving Completed
Columbia Gorge Parkway Roundabout Capital Paving Completed
Columbia Gorge Parkway Rollings Hills Road Bates Creek Drive Capital Paving Completed
Limerick Lane South Deerborn Circle Katy Lane Capital Paving Completed
Limerick Lane Katy Lane South End Capital Paving Completed
Ammonette Street Paris Road Old Highway 63 North Capital Paving Completed
McKee Street Rice Road Clark Lane Capital Paving Completed
Sylvan Lane Clark Lane Quail Drive Capital Paving Completed
Rothwell Drive Broadway Rollins Road Capital Paving Completed
Flatwater Drive Roundabout Capital Paving Completed
Forum Boulevard N. side of Hinkson Creek Bridge Stadium Blvd Capital Paving Completed

 

Columbia Public Works Street Division:

This is a tentative list of streets planned for mill and overlay by the Street Division this year but is subject to change. Streets are not final until operations are scheduled and announced.

Road From To Agency Schedule
Walnut Street
Fifth Street Sixth Street

Street Division

Completed

Bernadette Drive
North Stadium Boulevard  West Worley Street 

Street Division

Completed

Vandiver Drive Wabash Drive 

Oakland Gravel Road

Street Division

Completed

New Haven Road
 Lenoir Street South Rolling Hills Road

Street Division


Completed

South Rock Quarry Road Grindstone Parkway East Nifong Boulevard

Street Division

Completed

South Sinclair Road West Nifong Boulevard ~ 5550 S. Sinclair Road

Street Division

Completed

East Richland Road  St. Charles Road South Rolling Hills Road

Street Division

Completed

Moon Valley Road  Green Valley Drive

South End

Street Division

Completed

Sinclair Road  West Arrowhead Lake Drive

West Route K

Street Division

Completed

West Gillespie Bridge Road  Scott Boulevard

Chapel Hill Road

Street Division

Completed

Silvey Street   West Worley Street

Top of Hill

Street Division

Completed

Merideth Drive  Georgetown Drive

West End

Street Division

Completed

Callie Drive  West Millbrook Drive

North End

Street Division

Completed

Old Scott Boulevard   West Broadway Scott Boulevard

Street Division

Completed

Westwood Avenue   West Stewart Road

South End

Street Division

Completed

South Rolling Hills Road Old Millers Road ~4300 S. Rolling Hills Road

Street Division

Completed
Legion Lane – patching Near WW

Street Division

Completed
Rogers Street – patching

Street Division

Completed
Ash Street – patching Ninth Street 10th Street

Street Division

Completed

 