Lynn / Oak/ Sexton Sidewalk

Funding Fiscal Year: 
Design 2017/Construction 2019
Ward
1
Project Number:
C00685
Project Budget:
$213,000
Funding Source:
Capital Improvement Sales Tax / Community Development Block Grant
Year Completed:
 

 

Project Description: This project will fill in the sidewalk gaps along the block of Lynn Street, Oak Street and Sexton Road.

Project Status: BP Paterson began construction on the project the week of Sept. 16, 2019.

Project Manager: Allison Anderson, P.E.

Interested Parties Meeting: Nov. 15, 2016

Public Hearing: 

Press Releases:

Resources:


Construction Updates:

Nov. 18, 2019: The Lynn-Oak-Sexton Sidewalk is nearly complete with one drive entrance remaining to be completed later this week.

Oct. 3, 2019: The Lynn-Oak-Sexton Sidewalk project is about 40% complete. Sidewalks and driveways on Lynn and Sexton are complete. Contractor will be working the next couple of weeks on stormwater improvements and finishing up the sidewalk and driveways on Oak.

sidewalk construction

Sept. 24, 2019:  BP Paterson, the contractor for the Lynn-Oak-Sexton sidewalk capital improvement project, plans to close Oak Street between Sexton Road and Lynn Street to through traffic beginning Wednesday, Sept. 25. Residents have been notified and will be able to access their driveways from Oak Street. This closure is necessary for City of Columbia Water & Light to relocate a water line and for the contractor to complete construction of the sidewalk gaps along the block of Lynn Street, Oak Street and Sexton Road. Please watch for updates on social media or online and adhere to signs posted in the work zone. Motorists, nonmotorized transportation users and pedestrians are urged to use extreme caution in the work zone.

map showing location of oak street closure

Sept. 13, 2019:  

BP Paterson, the contractor for the Lynn-Oak-Sexton sidewalk capital improvement project, plans to begin construction Monday, Sept. 16, weather permitting. The project is estimated to take 45 days, weather permitting. Concrete sidewalks will be constructed to fill in the sidewalk gaps along the block of Lynn Street, Oak Street and Sexton Road. Some lane restrictions and a short-term closure on Oak Street will be required during the project. Please watch for updates on social media or online and adhere to signs posted in the work zone. The estimated investment is $213,000 paid for through the 2015 Capital Improvement Sales Tax ballot and a Community Development Block Grant. An interested parties meeting was held Nov. 15, 2016, and a public hearing before City Council took place Aug. 7, 2017. Motorists, nonmotorized transportation users and pedestrians are urged to use extreme caution in the work zone. Pedestrians will need to use alternate routes.

map showing lynn oak construction zone