Forum Boulevard Improvement (Green Meadows to Nifong)

    FUNDING FISCAL YEAR: 
    Design 2016-17/Construction 2020
    PROJECT NUMBER:
    C00653
    PROJECT BUDGET:
    $1,145,000
    FUNDING SOURCE:
    Joint City/County/State funds
    YEAR COMPLETED:
     

    Project Description: This project would widen the existing two-lane road to five lanes, add bike lanes and sidewalks along Forum and include storm water and utility improvements.

    Project Status: City staff is working on the concept plans for the corridor’s improvements.

    Project Manager: Nazmul Hussain, P.E.

    Interested Parties Meeting: To be held in conjunction with the Nifong Boulevard Corridor Improvement Project (Providence to Forum) IP Meeting on  Oct. 26, 2017, 5:30-7 p.m. at Gentry Middle School Cafetorium.

    Public Hearing: TBD
    Press Releases: 

    Location Map: Forum  (Green Meadows to Nifong) location

    Project Layout Concept: Forum (Green Meadows to Nifong) design-revised


    Return to Current CIP Projects