Capital Improvement Project: Paquin Park Improvements

Funding Fiscal Year: 2010
Project Number: C00447
Project Budget: $30,000
Funding Source: Park Sales Tax
Year Completed: 2010 – Planters
2013 – Concrete replacement

Project Description: Renovation of raised planter beds and replacement of concrete patio and walks, as needed.

Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537,

Council Items

Proposed Plan

Interested Parties Meeting: A public park planning meeting was held from 6:00-7:00pm, Thursday, November 19, 2009 at the ARC.

Project Notes: The City Council approved the project at the December 21, 2009 Council Meeting. Concrete replacement was delayed until parking lot issues were resolved.

Project Status: Project completed.

  • Constructed eight 4′ x 24′ planter boxes, installed fencing aroudn planter area, and placed in service for spring 2010 planting season.
  • Removed concrete steps and 30′ of walkway to open up the green space area.
  • Replaced broken concrete patio and walks. (See also ADA projects)

Paquin garden beds under construction
(Photo taken 4/8/10)
Completed garden beds and fencing
Concrete replacement
(Photo taken 10-15-13)

Paquin Park