Funding Fiscal Year: | 2017 |
---|---|
Project Number: | 00674 |
Project Budget: | $761,059* |
Funding Source: | $150,000 RTP Grant* $230,000 Park Sales Tax $381,059 PYA – Park Sales Tax* |
Year Completed: | 2018 |
* Mid-year fund transfer
Project Description: Replace wooden bridges on the MKT. Replace Bridges #5, 7, and 8, as recommended by the May 2013 MKT Bridge Engineering Study and Report.
Media Inquiries: Tammy Miller, Marketing Specialist, 573-874-7465, tammy.miller@como.govcreate new email
Project input: Mike Snyder, Park Planning Superintendent, 573-874-7204, mike.snyder@como.govcreate new email
Council Items:
Project Notes: A mid-year fund transfer was issued to close old projects (Project 00561: 2010 Annual Trails and 40113: Annual Greenbelt/Trails) and facilitate issuing the contract to include all three bridges.
See information regarding the trail detour.
Interested Parties Meeting: An interested parties meeting was held Thursday, September 21,2017 from 4:00 to 6:00 pm at the Martin Luther King Jr Memorial, 800 Stadium Blvd., Columbia, MO, 65203.
Project Status: Completed.
Major Vendors | ||||
---|---|---|---|---|
** | Vendor | Item | Purchase Order# | Amount |
C | Boone Construction | Replacement of Bridges #5, #7 and #8 | Contract 10/2018 | $619,599 |