Capital Improvement Project: Lake of the Woods Golf Course Driving Range Construction

Funding Fiscal Year: 2017 and 2018
Project Number: RS085
Project Budget: $70,000 FY2017
$50,000 FY2018
Funding Source: Golf Course Improvement Fees (GCIF)
Year Completed:

Project Description:
Construction of a driving range on 15 acres of land on the north side of the existing golf course. Construction will include grading, tee construction, irrigation and cart path installation.

Media Inquires: Tammy Miller, Marketing Specialist, 573-874-7465,

Project input: Matt Boehner, Sr. Park Planner, 573-874-7204,

Proposed Plans

Council Items

Interested Parties Meeting: An interested parties meeting was held on January 10, 2017 at the Lake of the Woods Golf Course and an online survey was conducted from January 9, 2017 to January 20, 2017. View the comments received.

Project Status: The driving range is near completion. Additional access connections will be completed this winter.

Major Vendors

Purchase Order#
C Selecturf Turf Materials 20170578 $19,775
C Rick Richardson Excavation Grading 20170335 $26,732
M Professional Turf Products Irrigation Equipment 20172481 $9,707
M Water & Sewer Supply Irrigation Equipment 20172460 $5,190
M Capital Sand Osage Gravel 20170948 $4,310
M MPR Supply Company Wire   $2,893

** C=Contract Work; P=Professional Services; M=Materials Only