Capital Improvement Project: Douglass Park Security Improvements

Funding Fiscal Year: 2012*
Project Number: C00505
Project Budget: $30,000
Funding Source: PYA Park Sales Tax
Year Completed: 2014

* Project approved mid-year. PYA = Prior Year Appropriation. Funds transferred from Annual Park Improvements: Providence Boardwalk Repair project.

Description: Replace two old security cameras and add two cameras to cover the pool and spraygrounds.

Project Manager: Mike Griggs, Assistant Director, 573-874-6398
mike.griggs@como.govcreate new email

Council Items

Interested Parties Meetings:

  • Douglass Neighborhood Association and Douglass High School, 9:00am, December 2, 2011 at Douglass High School
  • Douglass Park Forum, 6:00pm, January 18, 2012 at Douglass High School
  • Douglass Park Forum, 6:00pm, April 25, 2012 at Douglass High School

Project Notes: A report on the proposed project was presented at the July 16, 2012 Council Meeting. The Council directed staff to proceed with the installation of the security cameras.

Status: Project completed.

Major Vendors

**
Vendor
Item
Purchase Order#
Amount
C Integrated Solutions Security cameras and installation 122590 $18,094
C Water & Light Dept Fiber installation N/A $4,100
C Integrated Solutions Security cameras and recording storage 141073 $6,187

 

Douglass Park

Capital Improvement Program