Capital Improvement Project: Cosmo-Bethel New Shelter

Funding Fiscal Year: 2005
Project Number: C00218

Project Budget:

$130,000
Funding Source: $100,000 – 1999 1/4 Cent Sales Tax 
$30,000 – Force Account Labor
Year Completed: 2007

Council Items

Plans

Project Description: Construct new medium-sized reservable shelter with expanded patio and covered grill, 80-car lighted parking lot , and connecting sidewalks on southwest side of park. All work to be done with park force account labor, except for the earthwork and parking lot asphalt.

Project Notes: The garden plots were removed to make way for the new shelter and parking lot. 

Project Status: Completed. Shelter named Ficklin Shelter.

Major Vendors

Vendor
Item
Purchase Order#
Contract Amount
Richardson Excavation Earth work 061255 $8,810*
Boone Quarry Rock 072093 $19,249*
Central Concrete Concrete 052459 $11,932*
Frech Paving Asphalt parking lot 072168 $29,586**
Most Dependable Fountains Water fountain w/jug filler 072431 $2,330**
Fry & Associates Covered grill 072429 $511**

* Term and supply contract
** Amount for this project only; part of larger contract

 

80-car parking lot to serve the south shelter