Capital Improvement Project: Atkins Park Phase III

Funding Fiscal Year: 2016
Project Number: C00654
Project Budget: 2016 – $575,000
2017 – $75,000
Funding Source: Park Sales Tax
Year Completed: 2017

 

Project Description: Develop two additional fields and support amenities such as additional parking, batting cages, and walkways.

Media Inquiries: Tammy Miller, Marketing Specialist, 573-874-7465, tammy.miller@como.gov

Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537, toney.lowery@como.gov

Council Items

Interested Parties Meeting: Held January 21, 2016 from 5:00 pm to 7:00 pm at the Activity and Recreation Center, 1701 W. Ash Street, Columbia, MO 65203.

Preliminary Project Plans

Project Status: Complete.

Major Vendors

**
Vendor
Item
Purchase Order#
Amount
C Musco Sports Lighting Lighting 162017 $269,000
C Anchor Fence Company Fencing 20170857 & 162049 $151,900
C Christensen Construction Asphalt 20170907 $25,076
M Columbia Ready Mix Concrete 20170414 $12,902
M Boone Quarries Rock 161725 $38,819
C Rick Richardson Excavation Grading 161735 $34,673
M Water & Sewer Supply Irrigation Materials 160297 $3,768
M Mid Missouir Limestone Field Materials 130991 $7,488
M Capital Sand Mound Clay and Blocks   $4,406
C Harper Drilling Well Drilling and Installation 162048 $32,999