Capital Improvement Project: Antimi Sports Complex Improvements (2018)

Funding Fiscal Year: 2018
Project Number: RS087
Project Budget : $450,261
Funding Source: $450,000 – Park Sales Tax
$261 – Metal Recycling*
Year Completed:  2018
  • Mid-year appropriation

Project Description: Replace the existing backstops, fencing and dugouts on the original four fields, irrigate additional fields and make ADA walkway improvements.

Media Inquiries: Tammy Miller, Marketing Specialist, 573-874-7465, tammy.miller@como.govcreate new email

Project input: Toney Lowery, Sr. Park Planner, 573-874-7537 toney.lowery@como.govcreate new email

Interested Parties Meetings: Held on April 3, 2017 and April 4, 2017. An online survey was conducted from March 2, 2017 to April 14, 2017. View the comments receivedopens PDF file .

Project Master Planopens PDF file

Project Presentationopens PDF file

Council Items

Project Status: Substantially complete.  Fencing and field renovations have been completed and only minor improvements remain.

Major Vendors

**
Vendor
Item
Purchase Order#
Amount
C Anchor Fencing Fencing Contract 132/2017 $157,400
P Malicoat-Winslow Engineers Engineering Services 20180641 $938
C Rick Richardson Excavation Grading 20180750 $5,720
C Schaefer-Meyer Seed and Sod Field Grading 20173027 $14,612
M Columbia Ready Mix Concrete 20180749 $35,695
M Central Concrete Concrete 20180325 $2,007
M Con Agg / Boone Quarries Rock 20180473 $10,080
M Mid-Missouri Limestone Rock and Hauling 20180877 $4,693
M PlayCore / Play and Park Structures Shade Structures 20181091 $52,531
M Mid-MO Metals Steel 20181879 $5,343
M Dry Fork Steel Sign Frames and Foul Poles 20181478 & 20181368 $25,086
M Advanced Turf Solutions Dura Edge Filed Product 20181094 $29,513
M Nevco Sports Scoreboards 20181366 $11,581
M Gametime Athletics Back Stop Padding 20181664 $14,487
M BSN Sports 8 – 27′ Player Benches 20180649 $9,360
M Musco Sports Lighting Control Link Lighting System 20181204 $8,950
M Selecturf Turf Materials 20180882 $8,950
M A 1 Rental Equipment Rental Pcard $1,878
M Ahrens Steel and Welding Steel and Rebar Pcard $4,704
M Beelman Logistics Sand Pcard $1,761
M Bobat of St. Louis Bobcat Rental Pcard $1,496
M Carter Waters Filler, Bolts, Mesh Sheets, etc. Pcard $7,123
M Frost Electric PVC, Breakers, Lights, Tape, etc. Pcard $1,811
M Nets of America Nylon Netting Pcard $4,680
M James Fencing Fence Posts Pcard $6,504
M Wood Link Fence Co. Fencing Materials 20181945 $5,223
M Water and Sewer Supply Irrigation Supplies 20180055 $11,685
M Siteone Lanscape Irrigation Supplies Pcard $8,011
M Ri-Mor Topsoil Soil 20180746 $6,743
M Supreme Turf Products Turf Products Pcard $4,032
C Richardson Excavating Excavation Services 2018075 $5,720

** C=Contract Work; P=Professional Services; M=Materials Only