Capital Improvement Project: Antimi Sports Complex Improvements (2018)

Funding Fiscal Year: 2018
Project Number: RS087
Project Budget : $450,000
Funding Source: Park Sales Tax
Year Completed:  

Project Description: Replace the existing backstops, fencing and dugouts on the original four fields, irrigate additional fields and make ADA walkway improvements.

Media Inquiries: Tammy Miller, Marketing Specialist, 573-874-7465, tammy.miller@como.gov

Project input: Toney Lowery, Sr. Park Planner, 573-874-7537 toney.lowery@como.gov

Interested Parties Meetings: Held on April 3, 2017 and April 4, 2017. An online survey was conducted from March 2, 2017 to April 14, 2017. View the comments received.

Project Master Plan

Project Presentation

Council Items

Project Status: Fencing and field renovations have been completed.

Major Vendors

**
Vendor
Item
Purchase Order#
Amount
C Anchor Fencing Fencing Contract 132/2017 $166,700
P Malicoat-Winslow Engineers Engineering Services 20180641 $1,200
C Rick Richardson Excavation Grading 20180750 $5,720
C Schaefer-Meyer Seed and Sod Field Grading 20173027 $14,612
M Columbia Ready Mix Concrete 20180749 $5,031
M Mid-Missouri Limestone Rock and Hauling 20180877 $4,693
M PlayCore / Play and Park Structures Shade Structures TBD $52,531
M Advanced Turf Solutions Dura Edge Filed Product TBD $29,513

** C=Contract Work; P=Professional Services; M=Materials Only