Capital Improvement Project: American Legion Park – Replace Shelter and Playground

Funding Fiscal Year: 2017
Project Number: 0064
Project Budget: $100,000
Funding Source: Park Sales Tax
Year Completed:

Project Description: Replacement of existing shelter and playground at American Legion Park.

Media Inquiries: Tammy Miller, Marketing Specialist, 573-874-7465,

Project input: Toney Lowery, Sr. Park Planner, 573-874-7537

Council Items

Interested Parties Meeting: An interested parties meeting was held on January 10, 2017 at American Legion Hall and an online survey was conducted from January 9, 2017 to January 20, 2017. No comments were received online or at the meeting.

Proposed Plans

Project Status: Playground installation has been completed. New shelters have been ordered.

Major Vendors

Purchase Order#
M Playpower / All Inclusive Recreation Playground 20172273 $41,761
C Playpower / All Inclusive Recreation Playground Installation 20172836 $23,300
C Rick Richarson Excavation Grading 20170335 $1,245

** C=Contract Work; P=Professional Services; M=Materials Only