Funding Fiscal Year: | 2013 – $125,000 2014 – $10,000* |
---|---|
Project Number: | C00512 |
Project Budget: | $135,000* |
Funding Source: | Park Sales Tax |
Year Completed: | 2014 |
* Includes a $10,000 mid-year appropriation to contract construction of park sign on Blue Ridge Rd.
Project Description: Addition of a small restroom and sidewalks to serve west shelters, tennis courts and athletic fields. Project also included replacement of “Albert Park” signs and installation of a new park sign on Blue Ridge Road.
Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537
toney.lowery@como.govcreate new email
Proposed Plans: Restroom/Field Improvements – 8/14/12opens PDF file
Interested Parties Meeting: Held 6-7pm on Thursday, August 16, 2012 at the ARC, 1701 West Ash Street.
Project Notes: The project was approved at the October 1, 2012 Council Meeting.
Project Status: Completed.
Major Vendors | ||||
---|---|---|---|---|
** | Vendor | Item | Purchase Order# | Amount |
M | CST, Inc. | Pre-fab restroom | 131580 | $37,430* |
* Portion of PO for this project only.
** C=Contract Work; P=Professional Services; M=Materials Only