Funding Fiscal Year: | 2015 |
---|---|
Project Number: | C00591 |
Project Budget: | $125,000 |
Funding Source: | Park Sales Tax |
Year Completed: | 2016 |
Project Description: Develop neighborhood park on 5.28 acre property located at 3405 Zinnia Drive.
Project Manager: Matt Boehner, Sr. Park Planner, 874-7204, matthew.boehner@como.govcreate new email
Interested Parties Meeting: An IP meeting was held on October 7, 2014 at the ARC, 1701 West Ash Street. View commentsopens PDF file from this meeting.
Proposed Plans: Barberry Park Proposed Plans
opens PDF file
Major Vendors | ||||
---|---|---|---|---|
** | Vendor | Item | Purchase Order# | Amount |
P | Crocket Engineering | Engineering services | 151383 | $6,400 |
M | Fry & Associates | Shelter, tables and drinking fountain | 151643 | $22,306 |
C | Playpower | Playground Equipment | 152195 | $35,424 |
C | Richardson Excavation | Grading | 141688 | $10,553 |
C | Adiar Construction | Concrete Trail | 132073 | $25,620 |
M | Columbia Ready Mix | Concrete | 103721 | $10,123 |
M | Boone Quarries | Rock | 151186 | $4,090 |
** C=Contract Work; P=Professional Services; M=Materials Only
Project Status: Completed.