Capital Improvement Project: Armory Improvements – Flooring

Funding Fiscal Year: 2013
Project Number: C00513
Project Budget: $75,000
Funding Source: Park Sales Tax
Year Completed: 2013

Project Description: Project includes the replacement of the vinyl tile floor in the high-use meeting, locker and activity rooms with ceramic tile and rubber shock absorb flooring, installation of carpet in the offices, and replacement of the panic bars on the exit doors.

Project Manager: Mark Kottwitz, Park Supervisor, 573-874-6332, mark.kottwitz@como.gov

Council Items

Plans: Proposed plan – 11-12-12

Interested Parties Meeting: Held 5-7pm, November 13 at the Armory, 701 E. Ash Street.

Project Status: Completed.

Major Vendors

**
Vendor
Item
Purchase Order#
Amount
M House of Carpet Flooring 131499 $55,500
C Combined Flooring Carpet installation 131381 $3,337
M DH Pace Co. Panic bars 132057 $13,672

** C=Contract Work; P=Professional Services; M=Materials Only

New Armory Flooring
(Photo taken 2/5/2013)
New Armory Carpeting
(Photo taken 2/5/2013)