Capital Improvement Project: ADA Compliance – Parks

Funding Fiscal Year: 2012 – $157,240
2013 – $151,820
2014 – $100,000
2015 – $223,214
2017 – $207,000*
Project Number:

C00484

Project Budget: $839,274*
Funding Source: $839,274 – Park Sales Tax

* Pending City Council approval of the 2017 Capital Improvement Program.

Description: In 2011, the City of Columbia had an outside consultant complete an assessment of ADA compliance of City facilities. Over $800,000 in ADA compliance projects were identified for parks and recreation facilities. The projects ranged from lowering bathroom mirrors 1.5 inches to replacing sidewalks.

PARK ADA COMPLIANCE REPORTS

Again St. Park

Fairview Park Parkade Park
Albert-Oakland Park & Pool Grindstone Nature Area Parks Management Center
American Legion Park Highpointe Park Proctor Park
ARC Indian Hills Park Riechmann Pavilion
Armory Sports Center Kiwanis Park Rock Bridge Park
Bear Creek Park Lake of the Woods Rec Area Rock Quarry Park
Blind Boone Home Lions-Stephens Park Shepard Blvd. Park
Cosmo Park MKT Trail Stephens Lake Activity Center
Cosmo-Bethel Park MLK Jr. Memorial at Battle Garden Stephens Lake Park
Douglass Park Nifong Park Twin Lakes Recreation Area
Downtown Optimist Park Paquin Park Valleyview Park


Project Manager: 
Gabe Huffington, Park Services Manager, 573-874-7202, 
gabe.huffington@como.gov

Project Notes: In September 2011, 33 reports ranging from 6-34 pages each for parks and recreation facilities were made available to Parks and Recreation staff. Staff analyzed the reports and will prioritize and schedule the projects based on need, usage, feasibility, and funding. Work on some of the projects will begin in 2012. Some of the smaller items may be funded out of the annual park maintenance operating budget.

The new Federal guidelines regarding pool lifts came after the consultant completed the ADA compliance report for Columbia’s park system. The request for more ADA sidewalks at Stephens Lake Park also came after the report. These projects will also be incorporated into the Park ADA Compliance project.

Project Status: See chart below for ADA renovations completed. Plans are to incorporate ADA items in conjunction with current and upcoming capital improvement projects.

Park / Facility
ADA Report
Description of Work / Status Year Completed
ARC Completed two items: sidewalk repair and relocation of shelving unit near entry door.
2013
Again St. Park Completed all ten (10) ADA renovation items.
2012
Albert-Oakland Pool Completed installation of ADA pool lift.
Completed ADA restroom improvements.
2013
2017
American Legion Park Replaced playground pea gravel with engineered wood fiber.
2012
Raised lavatory in each restroom to 34″ a.f.f. to gain required clearance underneath.
2014
Armory Sports Center Completed 29 items related to the restrooms, doors, and other areas in the building.

2012

Cosmo Park Completed all nine (9) items for L.A. Nickell Clubhouse.
2013
Cosmo Park Steinburg Playground – Three exterior accessible route items. Also, a poured-in-place rubber safety surface was included in the renovation project to create an inclusive play area easily accessible for children with mobile disabilities. This aspect of the project is above the scope and in addition to the ADA items listed in the report.
2015
Replaced concrete pad at the Lamb Shelter drinking fountain for wheelchair access.
2014
Douglass Park Completed four (4) sidewalk items and five (5) parking items are no longer applicable with new parking plans for the Douglass Park Improvments Phase I Project.
2014
Douglass Pool Completed installation of ADA pool lift.
2013
Downtown Optimist Completed ADA walkways, added an ADA accessible picnic table and improved the wood fiber play surfaces (7 items total).
2015
Fairview Park Completed four items related to exterior accessible routes.
2015
Hickman Pool Completed installation of ADA pool lift.
2013
Lions-Stephens Park Completed ten items related to the playground and trail/sidewalks.
2012
LOW Pool Completed installation of ADA pool lift.
2013
LOW Recreation Area Added one wheelchair accessible picnic table at the pool and completed five (5) restroom items related to signage, mirrors, and dispensers.
2015
McKee St. Park
(not included in report)
Replaced playground pea gravel with engineered wood fiber.
2013
MKT Trail Installed a concrete pad for seating at the soccer field.
2015
MLK Jr. Memorial at Battle Garden Completed nine items related to the restrooms.
2015
Nifong Park Installed new concrete walkway from Cosmopolitan Breakfast Club Farm Animal Barn to the restroom.
2014
Paquin Park Completed three items related to the sidewalk.
2013
Parkade Park Replaced sidewalk adjacent to the W. Craig St.curb ramp and corrected slope.
2013
Rock Bridge Park Installed new contrasting truncated dome curb-cut at Marimare Lane and added a concrete walkway connecting to the play areas. Supplemented and compacted the existing wood fiber play surfaces in the two playgrounds.
2014
Shepard Blvd. Park Replaced playground pea gravel with engineered wood fiber.
2012
Removed worn decking and replaced playground.
2015
Stephens Lake Park New ADA walkways completed.
2012
Twin Lakes Recreation Area Completed 51 items in various locations, including the parking lot, restrooms, and bathhouse.
2013

Related Article:


Capital Improvement Program