In Fiscal Year 2018, $160,000 was budgeted for major park maintenance and small renovation or enhancement projects. Projects were submitted for approval in the Capital Improvement Program, as part of the budget process. Any unused fund balance is reserved for potential grant matches, other unanticipated projects that may require mid-year funding, or rolled over to the next fiscal year for future projects. The projects below were chosen for 2018 annual park improvement projects. Details on each individual project follow.
Funding Fiscal Year: | 2018 | |
---|---|---|
Project Number: | C00056 | |
Project Budget: | $160,000 | |
Funding Source: | Park Sales Tax | |
Projects Funded | ||
Project Number | Project Name | Amount Funded by 2018 Annual Parks |
00690 | Cosmo Handball Courts | $45,000 |
00696 | Cosmo Skate Park Improvements | $35,000 |
00697 | Emergency Phone Replacements | $20,000 |
00703 | Philips Park Trail and Landscaping Improvements | $60,000 |
Cosmo Handball Courts
Funding Fiscal Year: | 2018 |
---|---|
Project Number: | 00690 |
Project Budget: | $45,000* |
Funding Source: | Annual Parks – Park Sales Tax |
Year Completed: | Canceled |
*potential private donation pending.
Project Description: Project will include the construction of two handball courts in the park along with sidewalk improvements.
Media Inquiries: Tammy Miller, Marketing Specialist, 573.874.7465opens phone dialer, Tammy.Miller@CoMo.gov
Project Manager: Matt Boehner, Sr. Park Planner, 573.874.7204opens phone dialer, [email protected]create new email
Project Status: Project was not completed due to a lack of private donations and funds were returned to the Park Sales Tax fund balance.
Cosmo Skate Park Improvements
Funding Fiscal Year: | 2018 |
---|---|
Project Number: | 00696 |
Project Budget: | $35,000 |
Funding Source: | Annual Parks – Park Sales Tax |
Year Completed: | 2020 |
Project Description: Project will replace one existing feature at the skate park and repair multiple areas of broken/cracked concrete at the facility.
Media Inquiries: Tammy Miller, Marketing Specialist, 573.874.7465opens phone dialer, Tammy.Miller@CoMo.gov
Project Manager: Matt Boehner, Sr. Park Planner, 573.874.7204opens phone dialer, [email protected]create new email
Project Status: Completed.
Emergency Phone Replacements
Funding Fiscal Year: | 2018 |
---|---|
Project Number: | 00697 |
Project Budget: | $20,000 |
Funding Source: | Annual Parks – Park Sales Tax |
Year Completed: |
Project Description: Project will replace existing emergency phones at Stephens Lake Park (1) and the MKT Trail (2) with new blue light emergency phones to increase phone visibility to park and trail users and eliminate on-going maintenance of the 10+ year old existing phones.
Media Inquiries: Tammy Miller, Marketing Specialist, 573.874.7465opens phone dialer, Tammy.Miller@CoMo.gov
Project input: Mike Snyder, Park Planning Superintendent, 573.874.7203opens phone dialer,
Mike.snyder@CoMo.gov
Project Status: Phones have been completed except for installation of the phone at the MKT Forum trailhead.
Philips Park Trail and Landscaping Improvements
Funding Fiscal Year: | 2018 |
---|---|
Project Number: | 00703 |
Project Budget: | $60,000 |
Funding Source: | Annual Parks – Park Sales Tax |
Year Completed: |
Project Description: Project at Philips Park will include the construction of a bridge over the existing low water crossing on the lake trail, landscaping improvements at parking areas, signage and tree plantings at the park. As development continues around the park, staff has a need to improve trail and natural resources conditions on the property.
Media Inquiries: Tammy Miller, Marketing Specialist, 573.874.7465opens phone dialer, Tammy.Miller@CoMo.gov
Project Manager: 573.874.7537opens phone dialer, Toney.lowery@CoMo.gov
Interested Parties Meeting and Online Survey: An interested parties meeting was held on January 10, 2019 from 5:00 pm – 7:00 pm at the Boone County Historical Society, 3801 Ponderosa Street, Columbia, MO, 65201. An online survey was available from January 3, 2019 through January 17, 2019. Comments receivedopens PDF file
Project Status: Improvements are underway.