Pavement base repairs and mill and overlay operations planned for Worley Street and Ash Street, June 15-26

(COLUMBIA, MO) -

City of Columbia Public Works crews will be making pavement base repairs in preparation for the mill and overlay on Worley Street between North Garth Avenue and Bernadette Drive starting Monday, June 15 through Friday, June 26.

Capital Paving, contractor for the City of Columbia, will perform mill and overlay operations on Worley Street from North Garth Avenue to North Stadium Boulevard, and Ash Street from North Providence Road to Heather Lane beginning Monday, June 15 through Friday, June 19, weather permitting. Work will begin at 7 a.m. and end at 7 p.m.

Minor delays are expected due to lane restrictions, but streets will remain open to two-way traffic. Motorists, nonmotorized transportation users and pedestrians should exercise caution in these areas while crews are working. Flaggers will be present to assist motorists through the workzone when necessary.

This work is part of the 2020 Pavement Management Plan, which was presented to City Council in March 2020. This plan is based on the principle that preventive and rehabilitative street maintenance is more cost-effective than reconstruction.


City of Columbia Vision
Columbia is the best place for everyone to live, work, learn and play.

City of Columbia Mission
To serve the public equitably through democratic, transparent and efficient government.

-30-