[New Schedule] Summer surface seal operations scheduled for June 26-July 8

(COLUMBIA, MO) -

UPDATE DETAILS: Surface seal operations are scheduled to begin June 26. Musselman & Hall has released the following schedule,

subject to change due to weather or other work-flow factors:

 

Onyx Surface Seal Schedule - Musselman & Hall

Scheduled Date

Street

Section (link to location map)

June 26

Colonial       

(North end to Whitegate)

June 26

Craig

(Thurman to Garth)

June 26-27

Monroe   

(Old Hwy 63 to Paris Road)  

June 26-27

Sylvan

(Vandiver to Clark)

June 26-27

Stone         

(North end to Lakeview)    

June 27

Lincoln

(Oak to McBaine)

June 27-28

Leslie

(Providence to George)

June 27-28

Oakfield & Oak Meadows

(Oakfield Gravel Road to end)

June 28-29

Bernadette South

(Worley to Ash)

June 28-29

Parkside

(Creasy Springs to Schwabe)

June 28-30

Ash

(West Boulevard to Bernadette)

June 29-30

Rockcreek

(Longfellow to Rollins)

June 29-30

Mumford        

(North end to Faurot)    

June 30

Eastham

(Green Meadows to Brookline)

June 30 & July 3

Bradshaw

(Bray to Alsup)

June 30 & July 3

Greenbriar

(North end to Green Meadows Circle)

July 3

Madrid

(El Cortez to Seville)

July 3

Red Oak

 (Lynnwood to Oaklawn)

July 3 & July 5

Green Meadows

(Outer Road to Bethel)

July 3-8*

Oakland Gravel

(Brown School to Vandiver)

July 5

Southampton

(Lake Valley to Forum)

July 6-8

Old Hwy 63

(Stadium to Grindstone Parkway)

*Crews will not work on July 4.

RESOURCES:

 

Previous Press Releases

(June 21, 2017): 
Musselman & Hall, the contractor who will perform the surface seal operations this summer, has provided the following street maintenance schedule. This schedule is subject to change due to weather or other factors. Signs will be posted when it is time for residents to move vehicles off of the street. Please follow the instructions of flaggers and obey no parking signs when posted in the area. Vehicles left on the streets may be ticketed and towed at the owner's expense.


Original Press Release
(June 12, 2017):


Summer surface seal operations scheduled for 22 streets beginning June 20
Columbia Public Works announced Monday plans to surface seal a number of Columbia streets beginning June 20 with Onyx. The Onyx surface treatment is a fast-drying asphalt roadway and pavement sealing solution designed to extend pavement life. It is a mixture of liquid asphalt, fine aggregates, recycled products and bonding agents.

Musselman & Hall will apply the surface sealer for the City and provide traffic control. Minor delays are likely. Please follow the instructions of flaggers and obey no parking signs when posted in the area. Vehicles left on the streets may be ticketed and towed at the owner's expense.

Work will continue by the contractor during the summer until completed. The tentative order of streets will be announced as it becomes available from the contractor. Motorists, nonmotorized transportation users and pedestrians are asked to exercise caution in these areas while crews are working.



City of Columbia Vision
Columbia is the best place for everyone to live, work, learn and play.

City of Columbia Mission
To serve the public equitably through democratic, transparent and efficient government.

-30-